Construction log
2012-04-12   Work at the reception and on the ground floor of the building.

 
2012-03-27   First spring days at the construction site.

 
2012-03-07   The assembly of lighting on the façade, work is being performed inside the building.

 
2012-02-16   The last day of fixing the external façade and working inside the building.

 
2012-01-27   The start of real winter at the construction site.

 
2012-01-13   Mounting the facade and work on the water pond.

 
2011-12-29   The assembly of the façade on the western wall of the B1 building and the start of preparations for fitting suspended ceilings.

 
2011-12-14   The first external walls already without scaffolding.

 
2011-12-01   Developing the area around the B1 building.

 
2011-11-16   The first wall with the partly removed scaffolding; work inside the building.

 
2011-11-03   An access road, the facade, and laying infrastructural cables – numerous works are being conducted in parallel, to make it before winter.

 
2011-10-18   The facade assembly begins on the B1 building.

 
2011-10-04   The ceiling on the last storey of the B1 building.

 
2011-09-21   The construction of internal walls on the last storey and completing the work on the external wall structure in the B1 building.

 
2011-09-12   Erecting the scaffolding at one of the walls of the B1 building.

 
2011-08-30   Work is being continued on external walls of the third floor, while the ceiling construction is being prepared.

 
2011-08-23   Work on the third floor of the B1 building.

 
2011-08-09   Work on the second floor ceiling in the B1 building.

 
2011-07-14   Building work on external walls of the third floor in the B1 building.

 
2011-06-02   Commencing building work on external walls of the third floor in the B1 building.

 
2011-05-16   The first photos taken in the interior of the B1 building at the BCB Business Park.

 
2011-04-29   Work on the construction of external walls of the second floor in the B1 building.

 
2011-04-13   The B1 building is getting higher. The first floor is ready.

 
2011-03-31   The view of the BCB Business Park investment project from Lech Walesa Airport in Gdańsk Rębiechowo.

 
2011-03-24   Commencing construction work of external walls on the 1st floor in the B1 building

 
2011-03-09   The performance of work involved in constructing the walls of the B1 building ground floor.

 
2011-02-15   Work on the garage ceiling in the B1 building

 
2011-01-28   Reinforcement of the foundation plate B1 building

 
2010-12-20   Snowy December on the construction site of the BCB Business Park

 
2010-10-20   Commencing the construction of the B1 building at the BCB Business Park

 